Schedule logic

The dependencies connecting activities in a project schedule, including predecessor and successor relationships.

Why it matters

Relationships can link starts or finishes; a predecessor does not always need to finish before its successor starts. Constraints and lags affect the calculated dates and float.

In practice

A project example

Interior work starts progressively behind enclosure work using a defined start-to-start relationship.