Percent complete
An expression of progress against a defined scope or value basis at a stated date.
Why it matters
A cost-weighted percentage is not the same as the share of elapsed time or the number of tasks finished. Reports should distinguish observed physical progress from the contractor’s billed percentage.
In practice
A project example
Expensive equipment arrives before installation, increasing billed value without making the building equally closer to occupancy.