Contract time
The period or completion requirements established by the construction agreement, including properly authorized adjustments.
Why it matters
Check the commencement trigger, calendar, milestones, and extensions. A revised contractor schedule does not by itself revise a contractual completion date.
In practice
A project example
The forecast finish moves into December, but the approved contract completion date remains in November.