Construction · Defined

Front-loading

Assigning a disproportionate share of contract value to work billed early in a project. The resulting payments can run ahead of the value of work actually in place.

Why it matters

Not every large early expense is front-loading. Mobilization, deposits, and long-lead procurement may be legitimate if properly scoped and supported. The concern is whether the remaining contract balance reasonably supports the work still to be completed.

In practice

A project example

An early mobilization line carries a large amount while major installation lines are unusually low. The reviewer asks how the values were established and what remains funded.